Project: Orthopaedic Outpatient Centre
Client: James Paget University Hospitals NHS FT
Location: Great Yarmouth
The challenge
The Trust needed a same-day emergency care (SDEC) unit to bolster its urgent and emergency care offering. To provide the best patient flow through the current hospital building, the optimal location for the SDEC was next to the hospital’ emergency department (ED). The space neighbouring the ED was being used to house the Trust’s orthopaedic outpatient services.
Our solution
The Trust decided to move its existing orthopaedic services to a new On-Demand® facility, which neighbours its Orthopaedic Centre, a permanent building that Darwin Group also delivered and installed earlier this year. The Trust opted for an On-Demand solution as it wanted the flexibility and speed of a hireable facility, instead of investing in another permanent construction leading to future estate issues.
The completed building took 16 working weeks to deliver. Eight weeks were spent at a Darwin Group site in York, where the building was assembled and first and second fix works were undertaken.
A further eight-week onsite period followed, during which the modules were delivered, installed, and made fully watertight at James Paget Hospital. Following building installation, final onsite finishes were applied, including oak-finished doors and frames, floor-to-ceiling fire-rated windows, floor finishes with acoustic underlay, trunking, lighting, and suspended ceiling tiles.
The building was installed on a reduced-level dig with concrete pad foundations. Further groundworks included adapting and linking services and drainage within the existing hospital infrastructure and providing hard and soft landscaping alongside access ramps.

GIFA: 618m2

16 week programme

2.7m high ceilings

Fire safety compliant

Infection control compliant

IT hub

9x consultation rooms

Ancillary areas and utilities

HBN / HTM compliant